custom ad
NewsApril 19, 2005

City officials will unveil a new sanitation building Monday, meaning the sanitation department's trucks will now have a shelter. The six trucks have been parked outside since the May 6, 2003, tornado that destroyed the old building. The facility has 7,500 square feet of floor space for truck parking, storage, offices and a break room. ...

Receive Daily Headlines FREESign up today!

City officials will unveil a new sanitation building Monday, meaning the sanitation department's trucks will now have a shelter. The six trucks have been parked outside since the May 6, 2003, tornado that destroyed the old building. The facility has 7,500 square feet of floor space for truck parking, storage, offices and a break room. It is located at 510 Eastview Court near the recycling center. The building cost roughly $181,000. Klusner Concreters of Kelso installed the concrete for $40,781. Penzel Construction built the facility for $139,734. City employees from various departments constructed the inner room, installed flooring, lighting, plumbing and heating and also painted the interior.

Story Tags
Advertisement

Connect with the Southeast Missourian Newsroom:

For corrections to this story or other insights for the editor, click here. To submit a letter to the editor, click here. To learn about the Southeast Missourian’s AI Policy, click here.

Advertisement
Receive Daily Headlines FREESign up today!