Robinson Construction awarded contract

Robinson Construction Co. of Perryville, Mo., has been awarded a $5,515,800 contract from the city of Searcy, Ark., to make improvements to the city's wastewater treatment plant.

This is the second phase of the project. Robinson was also awarded phase one of the project, which was completed in September 2005.

Robinson Construction is a heavy construction and mechanical contractor serving the Midwest on a variety of project types.